How many days must owners notify adjacent property owners before starting deep excavations?

  1. 3 days

  2. 5 days

  3. 6 days

  4. 8 days

The correct answer is: 6 days

In the context of deep excavation projects, it is essential for property owners to notify adjacent property owners to ensure safety and allow them to prepare for any potential impacts. In North Carolina, the regulation specifies that owners must give a minimum notice of six days before commencing deep excavations. This notice period is crucial for maintaining good neighborly relations and ensuring compliance with local ordinances related to construction activities. The requirement for six days allows adjacent property owners the necessary time to understand the scope of the excavation, assess potential risks, and take any precautions if required. It reflects a balance between the need for construction to proceed in a timely manner while respecting the rights and peace of neighboring properties. Thus, six days is the standardized timeframe that construction laws in this context adhere to.